House Foundation Done Right

Blog post description.

HOME FOUNDATION

10/2/20242 min read

Souffront Contractors Inc
Souffront Contractors Inc

Step-by-Step Process for Foundation Phase Construction in Florida:

1. Site Preparation

  • Clearing and Grading: Remove trees, shrubs, and debris from the site. Grade the site to ensure proper drainage.

  • Excavation: Dig trenches or areas where the foundation will be laid, according to the building plans and local code requirements.

  • Soil Compaction: Compact the soil to prevent future settling, ensuring that the foundation has a stable base.

2. Soil Treatment

  • Termite Treatment: Apply termite protection chemicals as required by Florida Building Code to prevent infestations, particularly important for slab foundations.

  • Soil Moisture Protection: Ensure that the soil has proper moisture control by installing a drainage system if needed.

3. Installation of Moisture Barriers

  • Vapor Barrier (Moisture Barrier): Install a polyethylene sheet (typically 6 mils thick) to prevent moisture from penetrating the foundation slab. This is a required step to comply with Florida's building codes and prevent mold or structural issues.

  • Inspection Requirement: Have the vapor barrier installation inspected by a local building inspector before pouring the concrete.

4. Rebar Installation

  • Reinforcing Steel (Rebar): Lay out rebar according to the structural engineer's design. Rebar is essential for adding tensile strength to the concrete foundation.

    • Rebar Types: Use #4 or #5 rebar depending on structural requirements.

    • Spacing and Tying: Space the rebar correctly, usually 12-24 inches apart, and tie them securely using wire ties.

  • Grounding Electrode: Florida requires that a rebar section be grounded as part of the electrical system, so this step must be coordinated with the electrical contractor.

5. Foundation Inspections

Before proceeding with pouring concrete, multiple inspections must be completed:

  • Pre-Pour Rebar Inspection: The local building department will inspect the rebar layout to ensure it meets structural and code requirements.

  • Moisture Barrier Inspection: The vapor barrier must be inspected for proper installation.

  • Footing Inspection: The trenches or forms where concrete footings will be placed must be inspected for depth, width, and rebar placement.

6. Pouring the Concrete Foundation

  • Mixing and Pouring: Pour concrete over the rebar and moisture barrier, ensuring even distribution. The concrete should be a minimum of 2500 psi, as required by Florida codes.

  • Vibration and Smoothing: Use a vibrator to remove air bubbles and ensure the concrete is solid. Smooth the surface using trowels and floats.

  • Curing Process: Allow the concrete to cure properly, which typically takes 7-28 days depending on the weather and mix.

7. Post-Pour Inspections

  • Foundation Inspection: After the concrete is cured, an inspector will verify that the foundation was poured correctly and meets all structural and code requirements.

  • Slab Elevation: Depending on local ordinances, a survey may be required to ensure the slab's elevation is in compliance with flood zone regulations.

8. Other Required Reports

  • Soil Compaction Report: For some projects, especially larger commercial ones, a geotechnical engineer may need to provide a compaction report verifying that the soil is suitable for building.

  • Engineering Reports: Structural engineers may be required to submit reports on the foundation design, including rebar placement and load-bearing capacity.