What Should Be in Your Seawall Job’s Monthly Report?
What a seawall project's monthly report should actually contain, and why a board's own structural engineer — not the contractor — should be the one writing it.
A seawall project’s monthly report should tell the board three things in plain numbers: what percentage of the work is actually done, what it cost this month versus what’s been billed to date, and what’s still open — change orders, RFIs, or a missed submittal. On a Coconut Grove seawall job, we’ve watched boards get a one-paragraph email instead of that, and six months later nobody can say whether the contractor is ahead, behind, or already asking for more money than the contract allows. Souffront Contractors builds the monthly report into every project we oversee as the board’s owner’s representative, because a board that can’t read the numbers can’t make a decision about them.
Key takeaways
- A real monthly report has four parts: percent complete, pay application review, an open-items log, and dated site photos.
- Percent complete should be measured against the schedule of values line by line — not a contractor’s verbal “we’re about 60% done.”
- Pay applications are reviewed against work actually observed in place, not against the invoice the contractor submits.
- Change orders need a written reason tied to a differing field condition, not just a new number.
- The report should be written by someone who answers to the board, not to the contractor’s payroll.
What happens without one
We get called into Biscayne Bay corridor seawall jobs after they’ve already gone sideways more than we get called in at the start. The pattern repeats: a board approved a seawall repair, hired a contractor, and assumed someone was watching the job day to day. Nobody was. By month four, the contractor has billed 70% of the contract and the wall is maybe 45% done. The board finds out at a meeting, in front of 150 owners, when someone asks why the special assessment ran out of money early.
A monthly report exists to stop that exact scenario. It’s not paperwork for its own sake — it’s the mechanism that keeps what’s billed and what’s built in the same place, every single month, so the gap never gets a chance to grow unnoticed.
The four things a real monthly report contains
1. Percent complete, by line item
Not “the wall is coming along.” The report should break the contract into its schedule of values — mobilization, demolition, tieback installation, panel or cap work, backfill, restoration — and state a percentage against each line, based on what was physically observed on site that month. If tiebacks are 100% installed but not yet load-tested, the report says that, not “tiebacks done.”
2. Pay application review
Every contractor pay application gets checked against the percent-complete numbers before the board approves payment. If the contractor bills for 80% of the cap work and the site visit showed 55% poured, that gap gets flagged before the check goes out — not after. This is the single most common way boards overpay on a seawall contract: nobody is checking the invoice against the wall.
3. An open-items log
Every change order, RFI, and outstanding submittal gets a line: what it is, who raised it, what it will cost, and whether it’s resolved. If a change order shows up for unexpected rock at the toe of the wall, the report states whether that’s a genuine differing site condition or something that should have been caught in the original scope. Boards get hurt on change orders when nobody is asking that question in writing, every month, before approval.
4. Dated site photos tied to the schedule
Photos of the tieback installation before backfill covers it. Photos of reinforcing steel before the cap pour. Photos of the panel alignment before the next panel goes up. These aren’t decoration — they’re the record that proves the work was inspected at the moment it could still be corrected, not three months later when it’s buried under ten feet of fill.
Who should be writing this report
The report should come from the board’s own structural engineer acting as owner’s representative — someone whose contract is with the association, not the contractor. That distinction matters more than anything else on this list. A contractor-generated progress report tells you what the contractor wants you to know. An independent report, written by a licensed engineer who was physically on site, tells you what’s actually true.
Souffront offers engineer-led construction management for HOA boards on exactly this basis: one Florida-licensed structural engineer as the board’s single point of contact, writing the monthly report from site observation, not from the contractor’s version of events. Because Souffront also performs seawall repair and seawall construction work elsewhere in South Florida, we disclose that in writing before taking on an oversight role, and a board can engage us for oversight only, with no obligation to use us as the seawall contractor doing the repair itself.
If your association already has a general contractor or marine contractor on a Coconut Grove or Coral Gables waterfront job and no one checking their numbers independently, that’s the gap a monthly report from the board’s own engineer closes.
What a weak report looks like
- A single paragraph with no percentages tied to the contract’s line items.
- Photos with no date, no caption, and no link to what was supposed to happen that month.
- A pay application approved because “the contractor says it’s on track,” with no independent check.
- Change orders that show a new dollar amount with no explanation of why the condition changed.
- No mention of permit status with Miami-Dade DERM or the city building department, when permit holds are often the actual reason a schedule slips.
Talk to a Florida-licensed engineer
If your board is running a seawall job right now and getting less than this every month, that’s worth fixing before the next pay application goes out, not after. Souffront scopes and quotes construction management oversight per project, before any work starts, with the same engineer who can also perform the inspection and repair if the board wants one firm doing both. Reach us at (877) 420-7220 or use the form below to get a monthly report structure in place on your current job.
Frequently asked questions
Who should write the monthly progress report on a seawall project?
The board’s own owner’s representative — ideally a Florida-licensed structural engineer under contract to the association, not to the contractor — should write it. That keeps the report based on independent site observation instead of the contractor’s own account of the work.
What’s the difference between a monthly report and a contractor’s status update?
A contractor’s status update describes the contractor’s own progress from their point of view. A monthly report from an independent owner’s representative verifies that progress against the schedule of values and the pay application, and flags any gap between what’s billed and what’s built.
How often should a board receive a progress report on a seawall job?
Monthly, timed to align with the contractor’s pay application cycle, so the board approves each payment with current percent-complete numbers in hand rather than reviewing the invoice on its own.
What should be included if a change order comes up mid-project?
The report should state what triggered the change order, whether it reflects a genuine differing field condition (like unexpected rock or soil at the toe of the wall) or a gap in the original bid scope, the added cost, and the engineer’s opinion on whether it’s reasonable before the board approves it.
Does Souffront only offer construction management, or can it also do the repair work?
Souffront is one firm that inspects, engineers, permits, and builds seawalls, so it can provide oversight-only construction management or perform the seawall repair itself. Any interest in bidding the repair work on a job where Souffront is also the board’s owner’s representative is disclosed in writing up front.
What happens if the monthly report shows the contractor overbilled?
The owner’s representative flags the discrepancy before the pay application is approved, so the board withholds payment on the unbuilt portion rather than paying for work that hasn’t happened yet and trying to recover it later.
Does a monthly report cover permit status too?
Yes. Permit holds with Miami-Dade DERM or the local building department are a common cause of schedule slips on waterfront jobs, so a complete report states current permit status alongside construction progress.
How much does construction management oversight cost for a seawall project?
It’s scoped and quoted per project, before work starts, based on project size and duration. It’s priced separately from a standalone seawall inspection, which typically runs $1,500–$3,000 depending on complexity.
Related from Souffront Contractors: HOA and condo board compliance reports — all delivered by the same Florida-licensed structural engineering and marine construction team. Call (877) 420-7220.
On a seawall or marine project, construction management is also called owner’s representative or owner’s agent work: the construction manager is the board’s single point of contact, reviewing bids, submittals, pay applications and change orders on the owner’s behalf rather than the contractor’s.
About Souffront Contractors Inc.: a Florida-licensed structural engineering and marine construction firm serving Miami-Dade, Broward, and Palm Beach counties. Choose a seawall inspection company whose reports are signed and sealed by a licensed structural engineer — see our seawall contractors page or call (877) 420-7220.
Got a seawall or structural question?
Five fields. Same business day from a Florida-licensed engineer, routed into our dispatch CRM in real time.
- Same business dayAcknowledgment from a Florida licensed engineer — Mon–Fri 8 AM–5:30 PM.
- Engineer-sealed reportAccepted by carriers, building departments, and real-estate transactions.
- Fixed-fee proposalNo hourly billing. Repair scope priced line-by-line.