Which Seawall Contractor Delays Should Your Board Accept?

A field guide for Coral Gables and Biscayne Bay boards: which seawall contractor delays are legitimate, which aren't, and how to tell the difference.

Which Seawall Contractor Delays Should Your Board Accept?

Some seawall contractor delays are real and some are excuses dressed up as weather. A board should accept delays caused by permitting holds, material lead times, and conditions the contractor couldn’t have known about before digging. A board should push back on delays caused by thin crews, poor scheduling, or paperwork the contractor should have had ready months earlier. Souffront Contractors gets called into Coral Gables and Coconut Grove canal-front projects after the timeline has already slipped twice, and almost every time the board can’t tell which kind of delay they’re looking at.

Key takeaways

  • Weather days, permit review holds, and failed load tests are normal delays a board should expect and accept.
  • Crew no-shows, missing submittals, and “we’re waiting on materials” with no purchase order to prove it are the contractor’s problem, not the board’s.
  • Sheet pile and vinyl panel lead times in South Florida currently run 8–16 weeks and should be ordered before, not after, permit issuance.
  • A tieback that fails its torque test isn’t a delay to fight — it’s a safety finding that has to be corrected before backfill.
  • Boards without an engineer on their side average far longer disputes over the same change order than boards with one.

What a normal seawall timeline actually looks like

Most residential seawall jobs on Biscayne Bay move through four phases: permitting, mobilization, construction, and closeout. Permitting with Miami-Dade DERM alone can run 60 to 120 days depending on the scope and whether the project touches a submerged land lease. Add county or city building department review on top of that, and a board that expects crews on site six weeks after signing a contract is setting itself up for a fight that isn’t the contractor’s fault.

Material lead times are the other piece boards underestimate. Vinyl sheet pile and marine-grade concrete panels are currently running 8 to 16 weeks from order to delivery, and that clock should start the day the contractor has an approved permit set in hand — not the day the board starts asking why nothing has arrived.

Delays a board should accept

  • Permit review holds. If DERM or the city kicks a submittal back for a revision, that’s outside the contractor’s control. Ask for the correction letter and the resubmission date, not an apology.
  • Weather and tide windows. Sheet pile driving and underwater work on a Coconut Grove or Key Biscayne seafront lot depends on tide stage and sea state. A string of named storms in hurricane season is a legitimate delay, not a scheduling failure.
  • A failed load or torque test. Tiebacks get proof-tested before backfill. If one doesn’t hold, the fix — re-driving, re-grouting, or redesigning the anchor spacing — takes the time it takes. A special inspector signs off on that test independent of the installing contractor, and that sign-off matters more than the calendar.
  • Discovered conditions. Unmarked utilities, an old timber bulkhead buried behind the existing cap, or rock where the geotechnical report said sand — these show up only once excavation starts. They’re real delays with real cost, and they usually come with a legitimate change order attached.

Delays a board should push back on

  • “We’re short-handed this week.” Crew availability is the contractor’s business to manage, not the board’s to absorb. If a job sits idle for two weeks with no permit hold and no material backorder explaining it, that’s a staffing problem on their end.
  • Submittals that should’ve been ready at signing. Shop drawings, mix designs, and manufacturer cut sheets for the specified panel system aren’t a surprise requirement — they’re part of the contract. A contractor who’s still assembling submittals three weeks into the schedule was never ready to start.
  • Material delays with no paper trail. “The sheet pile is late” should come with a purchase order date and a supplier confirmation. If the contractor can’t produce one, the delay is a scheduling failure they’re pinning on a supplier.
  • Repeated no-shows with no written notice. One missed day happens. A pattern of missed days with no advance notice to the board is a performance issue, not a delay to accommodate.

Why this is hard for a volunteer board to call

A board of five homeowners with day jobs isn’t equipped to tell a legitimate tieback redesign from a contractor stalling for time, and that’s not a criticism — it’s not their profession. That’s the whole case for having a structural engineer on the board’s side of the table from bid through closeout, not just at the inspection stage. Engineer-led construction management means someone who reads the schedule, the submittals, and the daily logs is working for the association, not for the contractor pouring the wall.

That person — call it the owner’s representative, the project manager, or the board’s engineer — reviews the contractor’s updated schedule against the original, checks whether a claimed delay matches the permit record or the supplier’s own lead-time quote, and tells the board in plain terms whether a change order reflects a real differing condition or a gap the bid should have covered. Souffront both performs this oversight role and builds seawalls, so when a board engages Souffront to oversee a project built by another contractor, any interest in later bidding the work itself is disclosed in writing before the engagement starts — a board should expect that disclosure from anyone offering both services, in writing, not assumed.

What to ask for before you approve a delay

Before a board grants a time extension or approves a change order tied to a delay, ask for documentation, not an explanation over the phone:

  • A daily log showing what work happened, or didn’t, and why
  • Dated correspondence with the permitting agency if the hold is a permit issue
  • A supplier confirmation or purchase order if the hold is a material issue
  • Photos from the date of the claimed discovered condition
  • A revised schedule showing how the delay affects the completion date, not just an extension with no new milestones

A seawall contractor with a legitimate delay will have this paperwork ready without being asked twice. One without it is asking the board to take their word for it, which is exactly the position a volunteer board shouldn’t be in.

Talk to a Florida-licensed structural engineer

If your board is staring at a schedule that’s already slipped and can’t tell which delays to accept, get a structural engineer who didn’t write the original bid to look at the daily logs, the permit record, and the change orders before you sign off on anything. Souffront scopes construction management per project — quoted upfront, before the engagement starts — and serves boards across Coral Gables, Coconut Grove, Key Biscayne, and the rest of the Biscayne Bay corridor. Reach us at (877) 420-7220, or use the form below.

Frequently asked questions

How long should a seawall replacement actually take once permits are issued?

A typical residential seawall replacement in Miami-Dade or Broward runs 4 to 10 weeks of active construction once materials are on site, depending on wall length and whether underwater work is involved. The bigger variable is the permitting and material ordering period before construction starts, which often runs longer than the build itself.

Is a permit delay the contractor’s fault?

No. Once a complete application is submitted, review time with Miami-Dade DERM or the local building department is outside the contractor’s control. A contractor is responsible for submitting a complete, accurate application promptly — repeated rejections for incomplete paperwork are a different story.

What should a board do if a contractor blames “material delays” with no documentation?

Ask for the purchase order date and the supplier’s written lead-time confirmation. If the contractor can’t produce either, treat the claim as unverified and push for a firm revised completion date rather than an open-ended extension.

Can our inspection engineer also act as our owner’s representative during construction?

Yes, and many boards prefer it because the same engineer already knows the structure’s condition. If that engineer’s firm might also bid the repair work, the firm should disclose that interest in writing before the oversight engagement begins, so the board knows exactly what role is being paid for.

What happens if a tieback fails its load test — does that delay count against the contractor?

A failed test is a safety finding, not a contractor performance issue by itself. The time needed to re-drive, re-grout, or redesign the anchor is a legitimate delay. What a board should watch is how quickly the contractor responds once the special inspector reports the failure.

Should we include liquidated damages in a seawall contract to prevent delays?

Many boards do, tied to a defined substantial-completion date with carve-outs for permit holds, weather, and discovered conditions. The key is defining those carve-outs clearly in the contract so a legitimate delay and a liquidated-damages clock don’t end up in a dispute of their own.

How do we know if our seawall construction company is understaffing our job?

Ask for a daily log of crew size and compare it against the schedule’s assumed crew size. If a four-person crew schedule is consistently running with two people and no notice, that’s understaffing, not an unavoidable delay.

Does Souffront act as a general contractor or as the board’s representative?

Both, depending on what the board hires Souffront to do. As a licensed marine contractor, Souffront builds seawalls directly. As a construction manager, Souffront acts as the board’s representative overseeing a project — observing, reviewing, and advising, without taking on another contractor’s means, methods, or jobsite safety responsibilities. The engagement scope is defined in writing before work starts.

Related from Souffront Contractors: HOA and condo board compliance reports — all delivered by the same Florida-licensed structural engineering and marine construction team. Call (877) 420-7220.

Souffront works directly with the HOA board, the condo association and the property manager or CAM, delivering the documentation a board needs to act and to show it acted.

About Souffront Contractors Inc.: a Florida-licensed structural engineering and marine construction firm serving Miami-Dade, Broward, and Palm Beach counties. Arrange a seawall inspection in Broward County with same-week scheduling — see our seawall contractors page or call (877) 420-7220.

← All field notes

§ Talk to an engineer

Got a seawall or structural question?

Five fields. Same business day from a Florida-licensed engineer, routed into our dispatch CRM in real time.

  • Same business dayAcknowledgment from a Florida licensed engineer — Mon–Fri 8 AM–5:30 PM.
  • Engineer-sealed reportAccepted by carriers, building departments, and real-estate transactions.
  • Fixed-fee proposalNo hourly billing. Repair scope priced line-by-line.
Direct line

877 · 420 · 7220

Form 01 · Inspection Request Live · CRM Routed
5CY7ADe973cSLEl4WDCW · v1 Routes directly to dispatch CRM
§ 13 — Schedule

Schedule your inspection before a small repair becomes a structural repair.

Same-day response Signed & sealed reports Fixed-fee quotes Licensed & insured · FL Engineer Lic. No. 72462
Call 877 · 420 · 7220 Request Inspection